COMPLETED - Brick Kiln Creek bridge replacement

  • Project typeCapital Works
  • Project value$1,364,000
  • Project scheduleCompleted October 2022
Brick Kiln Bridge

Replacement of timber bridge with steel bridge.

Work commenced in January 2022 with the old timber bridge being removed with a temporary side track in place.

Contractors started work on construction of new bridge in February 2022 with work due to be completed by June 2022.

This project was funded under the Australia Government Bridges Renewal Program with a dollar for dollar grant.

 