  • Project scheduleWork commences 11 January 2021
  • Contractor nameQPRC
Businesses along Yass Road

The next stage of Yass Road resurfacing will commence on 11 January 2021.

This section will see the completion of the Queanbeyan-bound lanes from Endurance Avenue to the Bungendore roundabout. 

Work schedule

The work will be done as night works and proceed in sections:

  • Section 1 - Endurance Avenue to Silva Avenue - 11-13 January
  • Section 2 - Silva Avenue to Thurralilly Street - 14-18 January
  • Section 3 - Thurralilly Street to opposite the Bowling Club entrance - 19-20 January
  • Section 4 - opposite the Bowling Club entrance to Bungendore Road - 21-22 January

Following this there will be an intermediate layer applied for sections 3 and 4 from 25-27 January.  All sections will then receive a waterproof seal and application of the wearing surface from 28 January to 2 February.

All work is expected to be completed by the first week of February 2021.