MR270 - Captains Flat Road

  • Project typeCapital Works
  • Project value$10,000,000
  • Project scheduleWorks to commence in 2021/22 financial year
Map showing proposed areas of work along Captains Flat Road

We have received funding of $10,000,000 under the NSW Government's economic stimulus funding. Funds will be allocated:

  • $1,000,000 in 2020/21
  • $4,085,000 in 2021/22
  • $4,915,000 in 2022/23

This funding will provide 21km of resurfacing along Captains Flat Road.

 
 Grant
 Amount
 Project description
 Length  
 Cost  
 2020/21   $1m  Design, approvals and contingencies
   $1m  Completed
 2021/22   $4.085m  Pavement stabilisation and drainage widening 

 Completed
     Chainage 0.3km to chainage 5.8km  5.5km  $1.925m  Completed 
     Chainage 9.2km to chainage 12.3km  3.1km  $1.075m  Completed
     Chainage 12.3km to chainage 15.4km  3.1km  $1.085m  Completed
 2022/23  $4.915m  Pavement stabilisation and drainage widening      
     Chainage 16.7km to chainage 17.8km  1.1km  $0.52m  Completed
     Chainage 18.2km to chainage 21.3km  3.1km  $1.085m  Completed
     Chainage 22.3km to chainage 24.6km  1.3km  $0.81m  Completed
     Reconstruct and realign (level crossing section)      
     Chainage 21.3km to chainage 22.3km  1.0km  $1.0m  Completed
     Reconstruct, improve safety, resurface      
     Chainage 24.6km to chainage 26.9km  2.3km  $1.5m  

All chainages commence from Briars Sharrow Road.

 