The Management Plan covers a 1.4 km section of Turallo Creek from the Tarago Road bridge at the western end to where Turallo Creek crosses Turallo Terrace at the low-level crossing to the east.
Stage 1 - Clearing of willows and woody weeds from within the watercourse between Turallo Terrace (east end where road crosses Turallo Creek) and Tarago Road (west end) – Completed overall one large difficult willow near the Targao Road bridge to remove
Stage 2 - Removal of target weeds from the riparian zone adjacent to the current informal dog park – Partly completed, more work to be done in this area. It was delayed due to wet weather and boggy ground in the past few years.
Stage 3 - Currently targeting the area from the footbridge working upstream removing willows from the bank.
The Turallo Creek Management Plan(PDF, 2MB) details the staged approach that we have been working through to remove woody weeds from Turallo Creek in the Bungendore town centre.