COMPLETED Gidleigh Bridge replacement
- Project typeCapital works
- Project value$988,440
- Project scheduleCompleted 13 May 2021
- Contractor nameQPRC
- Completion Date28 June 2021
The Gidleigh Bridge replacement has now been completed and the new bridge commenced taking traffic on 13 May 2021.
It involves the replacement of the old timber bridge by a new INQUIK bridge which is part of the Council Bridge renewal program. The initial scope of the project includes the approach slabs and the sealing of both approaches (each 50m long). A further length may be sealed if budget permits.
Key elements of the Project
- Survey and design
- Erosion and Sediment Controls
- Side Truck Construction
- Site Establishment
- Demolition of Timber bridge
- Earthworks
- Pilling Works
- Abutment Pours
- Scour Protection
- Deck Pour
- Approach Slabs Construction
- Pavement upgrade – approaches
- Installation of road furniture for road safety requirements
- Demobilise and side truck removal
Project schedule (include times/days that the project will be worked on)
The construction will take place:
- 7am – 5pm, Monday to Friday and
- 7am – 2pm on weekends (if necessary)
The only approved work that may take place outside of these hours includes:
- Delivery of materials/components for safety reasons.
Emergency safety work to reduce the risk of harm to staff, drivers, property, and environment
Location
Gidleigh Lane, Bungendore 2621 View Map
-35.30913278714174, 149.471439983572
Gidleigh Lane ,
Bungendore 2621
Gidleigh Lane ,
Bungendore 2621
COMPLETED Gidleigh Bridge replacement
Photo Gallery