Project was completed June 2026

There is a culvert on Cooma Road, approximately midway between Jerrabattgulla Road and Harts Road, that was misaligned and required replacement.

Assistance had been provided through the jointly funded Commonwealth-state Disaster Recovery Funding Arrangements (DRFA) for the bedding material and pavement. Council funded the remaining costs to replace this structure.

Update 5 March

Cooma Road - the first half of the culvert ha been placed on the foundation. Work to place the second half will begin shortly.

Cooma-Rd-culvert-March-2026.jpg

Backfilling work March 2026

Update 6 February

Contractors have been preparing for a concrete pour of a base slab over the weekend 7-8 February. Once cured, box culverts will be placed and concrete for the surrounding formwork will be poured.