• Bungendore Waste Transfer Station -12 SEPTEMBER 2026 - 210 Tarago Road Bungendore - Saturday - 8am - 11am• Braidwood Waste Transfer Station -12 SEPTEMBER 2026 - 117 Bombay Road Braidwood - Saturday - 1pm - 4pm• Queanbeyan Waste Minimisation Centre -13 SEPTEMBER 2026 - 5 Lorn Road Crestwood - Sunday - 8am - 11am See our events page for more details.
This project is now complete. The project involved pavement rehabilitation, minor widening and sealing on old Cooma Road between Wellsvale Drive and Fernleigh Drive, Googong. This was funded by the Australian Government through the Roads to Recovery program.
Shoulder grading and site clearing works were completed in November 2025.
Drainage works were then completed in February 2026.
Road pavement works, including road base overlay and stabilisation were completed in March 2026..
Guardrail works were completed in April 2026.
Old Cooma Road Fernleigh to Wellsvale Drives, Googong 2620 View Map
Old Cooma Road Fernleigh to Wellsvale Drives , Googong 2620