Cooma Road Stony Creek Bridge Repairs

  • Project typeCapital Works
  • Project value$850,000
  • Project scheduleWork starts 21 January 2026 - Monday to Friday, 7am-4pm
  • Contractor nameHD Civil

Following the December 2023 flood event, Council received funding to repair the damaged Stony Creek Bridge on Cooma Road. Stony Creek Bridge is between Jerrabattgulla Road and Kain Cross Road. Emergency repair works were made initially in 2024, and our contractor is returning to complete the remainder of the scope of works.

Repairs are to the southern abutment and wingwall and northern wing wall and rock scour protection.

Work began on 21 January 2026, working Monday-Friday, 7am-4pm.

Please follow the directions of signage and traffic control during the work.

Assistance provided through the jointly funded Commonwealth-state Disaster Recovery Funding Arrangements (DRFA).

5 March update

The northern wingwall has been constructed and is being backfilled. Once this has been completed they will start work on the southern wingwall.

Contractors preparing for concrete pour at Stony Creek Bridge

 

Contractors preparing for concrete pour of wing wall in week of 9 February 2026