Old Cooma Road Fernleigh Drive to Wellsvale Drive

  • Project value$1,564.704
  • Project scheduleTo be completed by mid 2026

We are working on old Cooma Road between Wellsvale Drive and Fernleigh Drive, Googong.

There will pavement rehabilitation and minor widening and sealing, funded by the Australian Government through the Roads to Recovery program.

Shoulder grading and site clearing works were completed in November 2025.

Drainage works were then completed in February 2026.

Road pavement works, including road base overlay and stabilisation, began on Thursday 12 March. Contractors will be working from 6.30am-6pm. Sealing of a first section is expected on Friday 20 March, weather permitting. The crews will then return for four more days of work in the week of 23 March, before a another section is expected to be sealed on Friday 27 March, weather permitting.

Guardrail works are expected in early-mid April, depending on completion of the road works.

Location

Old Cooma Road Fernleigh to Wellsvale Drives, Googong 2620  View Map