Monaro Street is closed between Lowe Street and Atkinson Street with detours in place for the Monaro Street Refresh project.
Find out more
We’ve received reports of discoloured water in various locations across Queanbeyan, Jerrabomberra and Googong recently. First and foremost, we want to assure you that the water supply meets Australian Drinking Water Guidelines and is safe to drink. We are flushing water mains and working with Icon Water to investigate further.
New days and hours will soon be in place for our Waste Transfer Stations. Our busier transfer stations will be open longer and on more days. The changes make the hours more consistent across the transfer stations. All QPRC waste facilities will now be closed on NSW public holidays. Find out more about the new hours.
Waste Transfer Stations
Mulch at the Queanbeyan Waste Minimisation Centre will only be available for purchase until mid-August 2026. Compost, made from the green-lidded FOGO bin waste, will continue to be available for purchase.
We are working on old Cooma Road between Wellsvale Drive and Fernleigh Drive, Googong.
There will pavement rehabilitation and minor widening and sealing, funded by the Australian Government through the Roads to Recovery program.
Shoulder grading and site clearing works were completed in November 2025.
Drainage works were then completed in February 2026.
Road pavement works, including road base overlay and stabilisation, began on Thursday 12 March. Contractors will be working from 6.30am-6pm. Sealing of a first section is expected on Friday 20 March, weather permitting. The crews will then return for four more days of work in the week of 23 March, before a another section is expected to be sealed on Friday 27 March, weather permitting.
Guardrail works are expected in early-mid April, depending on completion of the road works.
Old Cooma Road Fernleigh to Wellsvale Drives, Googong 2620 View Map
Old Cooma Road Fernleigh to Wellsvale Drives , Googong 2620