The Braidwood and Bungendore Buy Back Centres will be closed this weekend, 1-2 August. The Waste Transfer Stations will remain open as normal - Braidwood 10am-4:30pm, Bungendore 8am-4:30pm.
Monaro Street is closed between Lowe Street and Atkinson Street with detours in place for the Monaro Street Refresh project.
Find out more
We’ve received reports of discoloured water in various locations across Queanbeyan, Jerrabomberra and Googong recently. First and foremost, we want to assure you that the water supply meets Australian Drinking Water Guidelines and is safe to drink. We are flushing water mains and working with Icon Water to investigate further.
New days and hours will soon be in place for our Waste Transfer Stations. Our busier transfer stations will be open longer and on more days. The changes make the hours more consistent across the transfer stations. All QPRC waste facilities will now be closed on NSW public holidays. Find out more about the new hours.
Waste Transfer Stations
Mulch at the Queanbeyan Waste Minimisation Centre will only be available for purchase until mid-August 2026. Compost, made from the green-lidded FOGO bin waste, will continue to be available for purchase.
Contractors are currently working on raising the reservoir walls. Wall construction is around 95% complete.
Upcoming work includes installation of power cables between Carolyn Jackson Drive and the reservoir site, pouring of concrete to join the wall panels and tensioning of the reservoir. The tank will then be filled to begin testing and the roof will be constructed.
Daily deliveries of materials continues, and for the safety of all we encourage people to take their headphones off when walking along the main access road below the reservoir site.
The project consists of:
The Jerrabomberra Reservoir is part of the Queanbeyan-Palerang Water Supply Scheme. It supplies water to the bulk of Queanbeyan. The existing Jerrabomberra Reservoir is a steel reservoir with a storage capacity of 22ML. This reservoir has now been in continuous service for in excess of 40 years and is in need of refurbishment. In addition to this, the site lacks sufficient storage in the event of supply interruption from Icon Water, a shortcoming identified in Council’s recently developed Queanbeyan Integrated Water Cycle Management Plan. To address these concerns, QPRC will construct a new reservoir to provide for additional water storage and to enable rectification works to be undertaken to the existing reservoir.
The works are located within the Jerrabomberra Mountain Reserve, a highly valued natural area. As such, the contractor will be required to maintain Jerrabomberra Hill Road for the duration of the works, and will also be required to manage their works to minimise the interruption to users of the reserve. The contractor will also be required to manage the environmental impacts in accordance with the approved Review of Environmental Factors.
The project is fully funded by Council from water charges and developer contributions.
The project timeframes are outlined below. All dates are indicative and may change.
Works will be undertaken during the following periods (except for the period of night work for concrete pours):
Demolition of auxiliary reservoir
Reservoir earthworks in progress - 13 November 2025
Reservoir earthworks in progress - 27 November 2025
Jerrabomberra Reservoir overnight concrete pour - 17 February 2026
Jerrabomberra Reservoir concrete curing - 18 February 2026
Jerrabomberra Reservoir concrete walls pour - 19 March 2026
Jerrabomberra Reservoir concrete walls - 19 March 2026
Jerrabomberra Reservoir - 2 April 2026
Jerrabomberra Reservoir walls being lifted in - 29 April 2026
Jerrabomberra Reservoir walls at end of day - 29 April 2026
Jerrabomberra Reservoir wall stitch joins - 28 May 2026
Jerrabomberra Reservoir walls tensioning - 25 June 2026
Jerrabomberra Reservoir completed walls - 25 June 2026
114 Jerrabomberra Hill Road, Jerrabomberra 2621 View Map
114 Jerrabomberra Hill Road , Jerrabomberra 2621