Henderson Road Stormwater Upgrade

  • Project typeCapital Works
  • Project value$2.86m
  • Project scheduleMonday to Friday, 7am-6pm
  • Contractor nameDale and Hitchcock Pty Ltd

Project update August 17

  • Works are now practically complete and the stormwater system is in operation.
  • Remaining tasks are to put the final seal down on Henderson Road, expected this week, weather permitting.
  • The area is currently open to traffic, but remains under the care of the contractor. 
  • Council has requested the contractor to sweep the road after the rain to remove loose rocks. 
  • Replacement of bollards around Railway Park are still yet to be complete. 
  • Seeding and landscaping have been held till later in the year when the weather warms up to encourage good grass establishment.
  • Two trees will be planted later this year by the Urban Landscapes team to replace a removed tree. 
Henderson Path

Project background

Stormwater on Henderson Road currently drains to an open channel within land owned by Transport for NSW. Council is responsible for the management of the easement, and the current arrangement has led to delays in maintenance and operational activities. This has led to stormwater issues for local properties.

To address these concerns, we are constructing a new stormwater main to redirect stormwater to an existing stormwater pipe. We are also installing a gross pollutant trap to improve stormwater quality.

HendersonRoad-1June-30June.jpg

 

Areas shown in red will be closed for the duration of the works for safety reasons. Path users will need to divert along the blue line during this period.