The first stage of this project was the sealing of 1.6km across two sections. This included 600m of Williamsdale Road from Badgery Road heading toward Keewong Lane and 1km from the unsealed section near Knowles Lane heading towards Burra. These works were funded by the Local Roads and Community Infrastructure Program. This has been completed.
We completed working on a 2.6km section between the sealed sections at the Monaro Highway end. The first seal was applied in late July 2024 with a final seal applied in December 2024, along with any defect repairs.
The NSW Government is funding the project on Williamsdale Road, with $2.99m under the Fixing Local Roads Program.
Williamsdale Road, Burra 2620 View Map
Williamsdale Road , Burra 2620