Queanbeyan Civic and Cultural Precinct

  • Project typeCapital Works
  • Project valueApproximately $74 million
  • Project scheduleDue for completion early 2023
  • Contractor nameADCO Constructions Pty Ltd
Artists impression of the front of the Queanbeyan Civic and Cultural Precinct

On 10 March 2021, Council accepted a recommendation to appoint ADCO Constructions to finalise the design and construct the Queanbeyan Civic and Cultural Precinct. Construction has now commenced. Regular construction notifications from ADCO will provide an update on the project status and can be found on this page. 

The redevelopment of 257 Crawford Street, Council’s old administration building is an essential component of Council’s CBD Transformation Strategy. Council staff are currently housed in 11 buildings across the CBD.

Name the tower crane colouring competition

We are running a naming and colouring-in competition to name the tower crane that will be used on the site of the Queanbeyan Civic and Cultural Precinct.

Download the colouring sheet here(PDF, 123KB)

Concept design

The concept design includes:

  • two towers (3 and 5 levels above ground and mezzanine)
  • connections to Bicentennial Hall and improved access to The Q theatre
  • approximately 6500m2 public realm
  • approximately 1450m2 community space
  • 2050m2 commercial space leased to NSW Government
  • 4000m2 council administration, including shopfront, public library space (integrating service desk and staff areas into head office)
  • meeting rooms and break-out spaces (for receptions and conference)
  • lettable commercial space (available initially for rental return, then for future QPRC growth)
  • gallery connecting office building to Bicentennial Hall and Q Theatre
  • approximately 100 car-space office and public basement parking
  • rooftop garden 

Council will take out a loan for the project, which will be paid for by merger savings, lease income and review of services. Council decided not to consider a special rate variation to service the debt for the head office.

Parking changes

Parking changes

During construction of the new Council building there will be changes to parking around the construction site. Parking options include:

  • Collett Car Park (entry via Collett/Morisset Streets) | all day parking
  • Showground Car Park (entry via Cooma Street) | all day parking
  • Rutledge Car Park (entry via Crawford/Rutledge/Collett Streets) | all day parking
  • Morisset Car Park (entry via Lowe/Morisset Streets) | timed parking
  • Lowe Car Park (entry via Lowe Street) | timed parking
Map showing parking around the QCCP construction site

 

 

Council has approved the Traffic and Pedestrian Management Plan for the QCCP. The Traffic Management Plan incorporates all stages of the QCCP project over the next eighty weeks to late March 2032. Traffic and pedestrian movement will be primarily impacted in Rutledge and Lowe Streets, and to a lesser extent in Crawford and Cooma Streets, for the duration of the QCCP project.

Timeline

2018

  • Internal Demolition - completed October 2018

2019

  • External Demolition - completed in June 2019

2019-2020

  • Concept Designs - prepared by Cox Architecture Pty Ltd
  • Community Consultation on concept designs and business case - October/November 2019 - completed December 2019
  • Development Approvals - lodged January 2020 - approved November 2020

2021-2022

  • Contract awarded to ADCO Constructions Pty Ltd - March 2021
  • Construction commenced in August 2021
   